(Created page with "#Prepare list of reliable volunteers [2 Months + June 17] (Jeff to compile, exec to provide info, Allen to reach out/confirm?) #Quantify Available Resources [2 week & simultaneou...") |
No edit summary |
||
| Line 10: | Line 10: | ||
#Incorporate Comments [1 day](Jeff) | #Incorporate Comments [1 day](Jeff) | ||
#Publish Plan for final Executive Review - July 22(Jeff to release) | #Publish Plan for final Executive Review - July 22(Jeff to release) | ||
[[File:2012CampaignPreliminaryPlanning.jpg|alt={"2012 Campaign Preliminary Planning Schedule"}|2012 Campaign Preliminary Planning Schedule]] | |||
Revision as of 13:27, 8 February 2012
- Prepare list of reliable volunteers [2 Months + June 17] (Jeff to compile, exec to provide info, Allen to reach out/confirm?)
- Quantify Available Resources [2 week & simultaneous with volunteer] (Jeff)
- Create Draft of the Campaign Plan [2 days + wait for info from June 17] [(Jeff, based on last campaign's material)
- Create list of major milestones
- Assign dates:some will be absolute, some will be relative to an assumption about the next election
- Resource load the plan using a fixed-task & flexible-task approach (Jeff)
- Review Draft with Leader & Deputy Leader [5 days] (Jeff, Allen, Paolo & Any exec's who volunteer)
- Incorporate Comments, schedule second review [1 day] (if warranted)
- Executive for Review [5 days] (Jeff to release, Exec to review)
- Incorporate Comments [1 day](Jeff)
- Publish Plan for final Executive Review - July 22(Jeff to release)